Isaca Exam CISA Topic 7 Question 73 Discussion

Actual exam question for Isaca's CISA exam
Question #: 73
Topic #: 7
[All CISA Questions]

During a project audit, an IS auditor notes that project reporting does not accurately reflect current progress. Which of the following is the GREATEST resulting impact?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Elfriede
12 months ago
Yes, if the project reporting is inaccurate, it may not meet the required quality standards.
upvoted 0 times
...
Samira
12 months ago
I'm worried that the project may not withstand a quality assurance review.
upvoted 0 times
...
Leonardo
12 months ago
That's true, without accurate information, decision-making becomes difficult.
upvoted 0 times
...
Ciara
12 months ago
I believe the project steering committee cannot provide effective governance without accurate reporting.
upvoted 0 times
...
Edda
12 months ago
Agreed, it can lead to project failure if not addressed properly.
upvoted 0 times
...
Letha
12 months ago
I think the impact of inaccurate project reporting is significant.
upvoted 0 times
...
Elenora
1 years ago
So, the correct answer would be C) The project steering committee cannot provide effective governance.
upvoted 0 times
...
Claribel
1 years ago
Yes, if the reporting is inaccurate, it would be difficult for the project steering committee to make informed decisions.
upvoted 0 times
...
Truman
1 years ago
I think the greatest impact would be that the project steering committee cannot provide effective governance.
upvoted 0 times
...
Laurel
1 years ago
I agree. It's crucial to understand the impact of inaccurate project reporting.
upvoted 0 times
...
Elenora
1 years ago
I feel like this question is really important for the exam.
upvoted 0 times
...
Jeannine
1 years ago
You know, if I was the project manager and my reporting was messed up, I'd be more worried about keeping my job than anything else. Just sayin'.
upvoted 0 times
...
Katina
1 years ago
Hmm, I see the logic in all of those options, but I think C is the most accurate. Without effective governance, the project is going to be a hot mess, no matter what else happens.
upvoted 0 times
...
Catarina
1 years ago
I don't know, I'm kind of leaning towards A. If the project manager is that incompetent, they might need to be replaced before the project can get back on track.
upvoted 0 times
...
Georgene
1 years ago
You guys are overthinking this. It's clearly D - if the project can't pass a QA review, it's going to be in big trouble. That's the biggest impact in my opinion.
upvoted 0 times
Carrol
1 years ago
I agree with the original comment, D is the most crucial.
upvoted 0 times
...
Xuan
1 years ago
B is also a pretty big issue.
upvoted 0 times
...
Dante
1 years ago
I disagree, A would cause the most trouble.
upvoted 0 times
...
Shawnda
1 years ago
I think C is the biggest impact.
upvoted 0 times
...
...
Carey
1 years ago
I disagree, I think B is the biggest impact. If the board of directors isn't getting the full picture, they could make some really bad decisions that could derail the entire project.
upvoted 0 times
Yan
1 years ago
I disagree, I think B is the biggest impact. If the board of directors isn't getting the full picture, they could make some really bad decisions that could derail the entire project.
upvoted 0 times
...
Barrett
1 years ago
D) The project will not withstand a quality assurance (QA) review.
upvoted 0 times
...
Jesus
1 years ago
C) The project steering committee cannot provide effective governance.
upvoted 0 times
...
Kelvin
1 years ago
B) The project reporting to the board of directors will be incomplete.
upvoted 0 times
...
Milly
1 years ago
A) The project manager will have to be replaced.
upvoted 0 times
...
...
Gwen
1 years ago
Oh man, this question is a tricky one. Inaccurate project reporting? That's a major issue. I'm leaning towards C, because if the steering committee can't provide effective governance, the whole project could go off the rails.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77