Which of the following is the BEST point in time to conduct a post-implementation review?

Show Suggested Answer Hide Answer
Suggested Answer: A

The best point in time to conduct a post-implementation review is after a full processing cycle. A post-implementation review is conducted to verify that the implemented system meets the original requirements and that it is operating as intended. Therefore, it is important to wait until the system has gone through a full processing cycle, so that any errors or issues can be identified and addressed. This allows the organization to make sure that the system is stable and reliable before it is put into production.


Contribute your Thoughts:

Ariel
11 months ago
That's a good point, Conducting the review right after deployment can help in identifying any early problems that may impact the project in the long run.
upvoted 0 times
...
Michael
11 months ago
I personally think conducting the review immediately after deployment is crucial because it allows us to address any immediate concerns or issues before they escalate.
upvoted 0 times
...
Barabara
11 months ago
I agree with conducting the review after a full processing cycle allows us to capture any issues or benefits that may arise during the entire cycle.
upvoted 0 times
...
Ariel
12 months ago
I think the best time to conduct a post-implementation review is after a full processing cycle.
upvoted 0 times
...
Isadora
1 years ago
Precious: A) After a full processing cycle gives us enough time to evaluate the impact
upvoted 0 times
...
Barrie
1 years ago
Stephen: C) After the warranty period may be too late to address any problems
upvoted 0 times
...
Dorothy
1 years ago
Zachary: B) Immediately after deployment could also work to catch any issues early
upvoted 0 times
...
Stephen
1 years ago
Precious: A) After a full processing cycle sounds like the best option
upvoted 0 times
...
Zachary
1 years ago
C) After the warranty period
upvoted 0 times
...
Precious
1 years ago
B) Immediately after deployment
upvoted 0 times
Devora
1 years ago
C) After the warranty period
upvoted 0 times
...
Tashia
1 years ago
A) After a full processing cycle
upvoted 0 times
...
Olga
1 years ago
B) Immediately after deployment
upvoted 0 times
...
...
Florinda
1 years ago
A) After a full processing cycle
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77