IIBA Exam CBAP Topic 1 Question 93 Discussion

Actual exam question for IIBA's CBAP exam
Question #: 93
Topic #: 1
[All CBAP Questions]

A major manufacturer of popular beverages has appointed a local distributor to serve a specific territory. The demand for the beverages has a pronounced seasonal pattern. The distributor performs well overall, but is repeatedly unable to keep up with fulfilling many customer orders during peak demand periods. The distributor's current delivery capability is stretched to deliver 60 tons of merchandise per day whereas the season's peak demand periods need a daily delivery capability of up to 100 tons.

The distributor is under pressure to fully meet the year-round market demand in order to stay in business. The distributor's management wants to identify and consider more cost-effective options as resorting to adding more trucks and drivers would not be economically feasible.

A business analyst (BA) has spent several days observing and measuring the warehouse activities to understand the situation and to gain insights into possible solutions. The delivery workflow is a four-step process: (1) picking the orders and assembling them on trays, (2) bringing the trays to the loading bay, (3) loading the orders into trucks, and (4) delivering the orders to customers. As the following table illustrates, overall performance depends is dependent on five major resources: (1) the workers who pick the orders and load them into trucks, (2) the tallyers who check the orders, (3) the drivers, (4) the trucks, and (5) eight loading bays (LBs).

Each truck can only make two trips a day. The BA has noticed that only 30% of trips have their orders available for loading when a truck arrives. Otherwise the truck has to wait one extra hour until the orders are picked and brought to the loading bay.

If trucks are the only constraint, approximately how many hours are lost due to this downtime?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Micaela
3 hours ago
I bet the answer is B) 20 hours. That just feels right to me, but I better double-check the math to be sure.
upvoted 0 times
...
Ruthann
4 days ago
Okay, let's think this through step-by-step. The key seems to be the 30% of trips where the orders aren't ready when the truck arrives. That's a lot of wasted time.
upvoted 0 times
...
Dorathy
1 months ago
Hmm, this seems like a tricky one. I need to carefully analyze the data and workflow to determine the downtime due to the trucks waiting.
upvoted 0 times
Samuel
2 days ago
I think it's around 20 hours based on the information provided.
upvoted 0 times
...
Bernadine
4 days ago
We need to figure out how many hours are lost due to the trucks waiting.
upvoted 0 times
...
...
Polly
1 months ago
But if the trucks are the only constraint, then it must be A) 18 hours.
upvoted 0 times
...
Franklyn
1 months ago
I disagree, I believe the answer is B) 20 hours.
upvoted 0 times
...
Polly
2 months ago
I think the answer is A) 18 hours.
upvoted 0 times
...

Save Cancel