IASSC Exam ICGB Topic 9 Question 60 Discussion

Actual exam question for IASSC's IASSC Certified Lean Six Sigma Green Belt exam
Question #: 60
Topic #: 9
[All IASSC Certified Lean Six Sigma Green Belt Questions]

The reported Cpk for a process with an average of 94 units, a spread of 22 units and upper and lower specification limits of 125 and 80 units would be?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Ivette
1 days ago
I agree, Cpk can be confusing. I think the formula involves the average, spread, and limits.
upvoted 0 times
...
Annett
2 days ago
This question is tricky, I'm not sure about the Cpk calculation.
upvoted 0 times
...