Independence Day Deal! Unlock 25% OFF Today – Limited-Time Offer - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

GIAC Exam GISF Topic 5 Question 47 Discussion

Actual exam question for GIAC's GISF exam
Question #: 47
Topic #: 5
[All GISF Questions]

You are the project manager of a new project in your organization. You and the project team haveidentified the project risks, completed risk analysis, and are planning the most appropriate riskresponses. Which of the following tools is most effective to choose the most appropriate riskresponse?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Gilma
1 months ago
Decision tree analysis? More like decision tree 'wow, this is really helpful!' am I right? *winks*
upvoted 0 times
...
Ardella
1 months ago
Delphi Technique? What is this, a cult meeting? I'll stick with the good old decision tree analysis, thank you very much.
upvoted 0 times
...
Jody
1 months ago
Project network diagrams? Really? How are those going to help me pick a risk response? I'm going with decision tree analysis - it's the perfect tool for this job.
upvoted 0 times
Amira
16 days ago
That's true, decision tree analysis can be a powerful tool in decision-making processes. It's important to consider all available options before making a final decision.
upvoted 0 times
...
Olive
17 days ago
I see your point, but decision tree analysis can also help in evaluating different possible outcomes and their probabilities, making it easier to choose the best risk response.
upvoted 0 times
...
Bettyann
18 days ago
Project network diagrams can help visualize the sequence of activities and dependencies, which can be crucial in identifying the most appropriate risk response.
upvoted 0 times
...
...
Cathrine
2 months ago
Cause-and-effect diagrams are great for identifying the root causes of risks, but they don't really help me choose the right response. I think decision tree analysis is the tool I'd use here.
upvoted 0 times
Therese
18 days ago
I see your point, but I still think Delphi Technique could be effective in reaching a consensus among experts on the best risk response.
upvoted 0 times
...
Antonette
25 days ago
I think project network diagrams could also be useful in visualizing the sequence of activities and their dependencies in risk response planning.
upvoted 0 times
...
Ashanti
1 months ago
I agree, decision tree analysis helps in evaluating different response options and their potential outcomes.
upvoted 0 times
...
...
Julian
2 months ago
Decision tree analysis sounds like the way to go. It helps evaluate the probability and impact of risks, and choose the best response strategy.
upvoted 0 times
Isaac
1 months ago
I think using cause-and-effect diagrams could also be helpful in identifying the root causes of risks.
upvoted 0 times
...
Glen
1 months ago
I agree, decision tree analysis is a great tool for evaluating risks and responses.
upvoted 0 times
...
...
Twanna
2 months ago
I prefer using the Delphi Technique, it involves expert opinions for better risk response planning.
upvoted 0 times
...
Magda
2 months ago
I agree with Rosenda, Decision tree analysis helps in making informed decisions.
upvoted 0 times
...
Rosenda
3 months ago
I think the most effective tool is Decision tree analysis.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77