GIAC Exam GISF Topic 3 Question 51 Discussion

Actual exam question for GIAC's GISF exam
Question #: 51
Topic #: 3
[All GISF Questions]

The executive team wants you to track labor costs for your project as well as progress on task

completion and the resulting dates. What information must you update for tasks to provide this

information?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Paris
17 days ago
Option C seems like the most comprehensive answer. Actual Start, Actual Work, and Remaining Work would give me the information I need to track labor costs and task completion progress.
upvoted 0 times
...
Emilio
20 days ago
I think the answer is D) Actual Start, Percent Complete, and Remaining Duration because it provides a comprehensive view of labor costs and progress.
upvoted 0 times
...
Paul
21 days ago
I disagree, I believe the answer is A) Start, Work, and Remaining Work.
upvoted 0 times
...
Edgar
24 days ago
I think the answer is C) Actual Start, Actual Work, and Remaining Work.
upvoted 0 times
...