What does a SPI value greater than 1.0 indicate?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Ludivina
7 days ago
Hmm, a SPI over 1.0 indicates a cost underrun. I wonder if the project manager has been skimping on the coffee budget again.
upvoted 0 times
...
Ronald
10 days ago
Well, duh! A SPI over 1.0 is a clear sign that the project is ahead of schedule. Now if only my boss would understand that.
upvoted 0 times
...
Lenita
15 days ago
I'm not sure, but I think it makes sense that if the SPI is greater than 1.0, it means more work was completed than planned.
upvoted 0 times
...
Reid
17 days ago
I agree with Chu, option A seems to be the correct answer.
upvoted 0 times
...
Bernadine
18 days ago
A SPI greater than 1.0 means more work was completed than planned. Looks like someone's been burning the midnight oil!
upvoted 0 times
...
Chu
25 days ago
I think a SPI value greater than 1.0 means more work was completed than planned.
upvoted 0 times
...