GAQM Exam PPM-001 Topic 4 Question 99 Discussion

Actual exam question for GAQM's PPM-001 exam
Question #: 99
Topic #: 4
[All PPM-001 Questions]

Which of the following is NOT included in a schedule change control system?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Norah
28 days ago
I was just about to select D, but then I remembered that a change control system needs to have some boundaries, so that's gotta be the wrong answer.
upvoted 0 times
Janey
8 days ago
User 2: I agree, C seems like the odd one out.
upvoted 0 times
...
Youlanda
9 days ago
User 1: I think it's C, because paperwork is usually required for making changes.
upvoted 0 times
...
...
Hildred
1 months ago
I'm going with B. Tracking systems. How else are you supposed to, you know, track the changes?
upvoted 0 times
...
Adell
1 months ago
D seems like the odd one out here. A schedule change control system is all about managing the process, not the actual changes themselves.
upvoted 0 times
Truman
11 days ago
B) Tracking systems
upvoted 0 times
...
Iluminada
21 days ago
A) Approval levels necessary for authorizing changes
upvoted 0 times
...
...
Vallie
2 months ago
Hmm, I think the answer is C. Paperwork necessary for making changes. That's a key part of the change control process.
upvoted 0 times
Mila
1 days ago
User 3: I agree with Mila, D seems like the correct answer.
upvoted 0 times
...
Anisha
13 days ago
User 2: No, I believe it's D. Limitations on the scope of changes.
upvoted 0 times
...
Brett
30 days ago
User 1: I think the answer is C. Paperwork necessary for making changes.
upvoted 0 times
...
...
Wayne
2 months ago
I disagree, I think it's D) Limitations on the scope of changes, because that's important for controlling changes.
upvoted 0 times
...
Lai
2 months ago
I agree with Natalya, because paperwork is usually required for making changes.
upvoted 0 times
...
Audria
2 months ago
I'm pretty sure the correct answer is D. Limitations on the scope of changes. That's not usually part of a schedule change control system.
upvoted 0 times
Lonna
25 days ago
Yeah, limitations on the scope of changes doesn't sound like it belongs in a schedule change control system.
upvoted 0 times
...
Brock
1 months ago
I agree, D seems like the odd one out.
upvoted 0 times
...
...
Natalya
2 months ago
I think the answer is C) Paperwork necessary for making changes.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77