GAQM Exam PPM-001 Topic 11 Question 110 Discussion

Actual exam question for GAQM's PPM-001 exam
Question #: 110
Topic #: 11
[All PPM-001 Questions]

Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Farrah
27 days ago
I don't know about you, but I'm just hoping I don't have to fast track my way out of a job after this exam. Gotta love the project management life, am I right?
upvoted 0 times
...
Serita
28 days ago
I'm going to have to go with B. The critical path will have positive total float. Sounds counterintuitive, but hey, that's project management for you!
upvoted 0 times
Gladys
4 days ago
I see your point, but I still think B) The critical path will have positive total float.
upvoted 0 times
...
Ciara
9 days ago
Actually, I'm leaning towards D) Duration buffers are added to maintain a focus on planned activity durations.
upvoted 0 times
...
Kate
11 days ago
I disagree, I believe C) Contingency reserves are released for redeployment by the project manager.
upvoted 0 times
...
Corinne
11 days ago
I think A) The risk of achieving the shortened project time is increased.
upvoted 0 times
...
...
Donette
1 months ago
This is a tricky one, but I'm going with D. Duration buffers are added to maintain a focus on planned activity durations, which is a smart move when fast tracking.
upvoted 0 times
Brandon
12 days ago
A) The risk of achieving the shortened project time is increased.
upvoted 0 times
...
...
Sherrell
2 months ago
Hmm, that makes sense too. Fast tracking can lead to risks, but it can also free up resources for other areas of the project.
upvoted 0 times
...
Myra
2 months ago
I disagree, I believe the answer is C) Contingency reserves are released for redeployment by the project manager.
upvoted 0 times
...
Selma
2 months ago
C seems like the correct answer to me. Contingency reserves can be released for redeployment, which is a logical consequence of fast tracking.
upvoted 0 times
Danilo
25 days ago
C) Contingency reserves are released for redeployment by the project manager.
upvoted 0 times
...
Carole
1 months ago
A) The risk of achieving the shortened project time is increased.
upvoted 0 times
...
...
Mari
2 months ago
I think the correct answer is A. Fast tracking increases the risk of achieving the shortened project time. That's just common sense, right?
upvoted 0 times
...
Sherrell
2 months ago
I think the answer is A) The risk of achieving the shortened project time is increased.
upvoted 0 times
...

Save Cancel