Question #: 75
Topic #: 10
[All PPM-001 Questions]

What is the expected activity cost for a project having a most likely cost of $140, a best case scenario of $115, and a worst case scenario of $165?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Reuben
1 months ago
I don't know about you, but I'm feeling a bit 'cost-conscious' today. Maybe we should just flip a coin and call it a day?
upvoted 0 times
Ronald
15 hours ago
I agree, let's go with $138 for the expected cost.
upvoted 0 times
...
Sharika
2 days ago
Looks like the expected activity cost is $138. Let's go with option B)
upvoted 0 times
...
Lottie
7 days ago
So, (115 + 4 * 140 + 165) / 6 = $138
upvoted 0 times
...
Odette
28 days ago
I think the expected cost is $138 as well.
upvoted 0 times
...
Susana
1 months ago
Let's not leave it up to chance, the expected cost is $138.
upvoted 0 times
...
Janessa
1 months ago
Let's calculate the expected activity cost using the formula: (best case + 4 * most likely + worst case) / 6
upvoted 0 times
...
...
Rima
2 months ago
D) $165? Only if I'm planning a party for the project manager's retirement. This isn't the worst-case scenario, it's the 'let's add a hefty contingency' scenario.
upvoted 0 times
...
Weldon
2 months ago
A) $115? Really? Maybe if I had a time machine and could guarantee the best-case scenario. Otherwise, I'll have to pass on that one.
upvoted 0 times
Louis
7 days ago
D) I would go with option C) $140 as the expected activity cost.
upvoted 0 times
...
Kristel
9 days ago
C) I agree, the expected cost is usually closer to the most likely scenario.
upvoted 0 times
...
Laurel
14 days ago
B) I think the expected activity cost would be closer to the most likely cost of $140.
upvoted 0 times
...
Michal
1 months ago
A) $115? Really? Maybe if I had a time machine and could guarantee the best-case scenario. Otherwise, I'll have to pass on that one.
upvoted 0 times
...
...
Anglea
2 months ago
I'm going with B) $138. The expected cost should be somewhere between the best and worst case scenarios, right?
upvoted 0 times
Tarra
24 days ago
I agree with you, the correct answer is C) $140.
upvoted 0 times
...
Eleonora
26 days ago
I think it's C) $140. The expected cost is calculated using the formula (best case + 4 * most likely + worst case) / 6.
upvoted 0 times
...
...
Trina
2 months ago
C) $140 seems like the obvious choice here. It's the most likely cost, so why overthink it?
upvoted 0 times
...
Avery
2 months ago
That makes sense. So, the answer would be C) $140.
upvoted 0 times
...
Pamella
2 months ago
So, the expected cost would be ($140 + $115 + $165) / 3 = $140.
upvoted 0 times
...
Noelia
2 months ago
I think the expected activity cost is the average of the most likely, best case, and worst case scenarios.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77