GAQM Exam CSM-001 Topic 4 Question 64 Discussion

Actual exam question for GAQM's CSM-001 exam
Question #: 64
Topic #: 4
[All CSM-001 Questions]

You are the Scrum Master. The Sprint will complete in two days. Each day of the Sprint is equivalent to 8 hours. The team has just enough time to complete all tasks in the remaining 16 hours with the exception of three tasks. Of these three tasks, two tasks (a total of 6 hours) are required to complete one Product Backlog item and one task (an estimate of 2 hours) is required to complete another Product Backlog item. How should the development team handle the remaining three tasks?

Show Suggested Answer Hide Answer
Suggested Answer: C, D, G

Contribute your Thoughts:

Sol
1 months ago
Option D sounds like a great way to start the next Sprint on the wrong foot. Let's be smart and go with C. The Product Owner can always re-prioritize those items for the next Sprint.
upvoted 0 times
...
Martina
1 months ago
Haha, the 'work extra 8 hours' option is a classic. I'm sure the team would love that idea, but it's not sustainable. Placing the incomplete items back on the Product Backlog is the way to go.
upvoted 0 times
Maynard
11 days ago
Yeah, working extra hours is not the best solution. Let's focus on what's sustainable for the team.
upvoted 0 times
...
Pedro
15 days ago
C) The development team should place the two Product Backlog items back onto the Product Backlog
upvoted 0 times
...
Denise
16 days ago
A) The development team should negotiate with the Product Owner on the definition of 'done'.
upvoted 0 times
...
...
Larue
2 months ago
Option B seems like a risky move. Working extra hours to complete the commitment could lead to burnout. I think the team should be realistic and move the unfinished items back to the Product Backlog.
upvoted 0 times
Renato
2 days ago
That sounds like a more sustainable approach. We can then prioritize those items in the next Sprint.
upvoted 0 times
...
Noah
13 days ago
I agree, burnout is a real concern. Maybe we should consider option C and move the unfinished items back to the Product Backlog.
upvoted 0 times
...
Tawna
16 days ago
Let's discuss with the Product Owner for clarity.
upvoted 0 times
...
Jerry
20 days ago
Option B seems like a risky move. Working extra hours to complete the commitment could lead to burnout.
upvoted 0 times
...
Jaime
29 days ago
Agreed. Moving unfinished items back is more realistic.
upvoted 0 times
...
Rosalind
1 months ago
Option B seems risky. Burnout is a concern.
upvoted 0 times
...
...
Aileen
2 months ago
I agree with option C. Putting the unfinished items back on the Product Backlog is the best way to handle this situation. Maybe the Product Owner can reevaluate the priority of those items for the next Sprint.
upvoted 0 times
...
Antonio
2 months ago
I disagree. We should negotiate with the Product Owner on the definition of 'done' to see if there's any flexibility.
upvoted 0 times
...
Angella
2 months ago
The development team should place the two Product Backlog items back onto the Product Backlog. This is the correct answer as it allows the team to focus on completing the tasks they can finish within the remaining 16 hours and re-evaluate the two incomplete items for the next Sprint.
upvoted 0 times
Aleta
21 days ago
C
upvoted 0 times
...
Tashia
22 days ago
A
upvoted 0 times
...
Josefa
29 days ago
C
upvoted 0 times
...
Man
1 months ago
A
upvoted 0 times
...
...
Precious
2 months ago
I agree with Mammie. It's important to deliver on our commitment to the Product Owner.
upvoted 0 times
...
Mammie
2 months ago
I think we should work the extra 8 hours to complete our commitment.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77