Deal of The Day! Hurry Up, Grab the Special Discount - Save 25%
- Ends In
00:00:00
Coupon code:
SAVE25
X
Welcome to Pass4Success
Login
|
Sign up
-
Free
Preparation Discussions
Mail Us
support@pass4success.com
Location
PL
MENU
Home
Popular vendors
Salesforce
Microsoft
Nutanix
Cisco
Amazon
Google
CompTIA
SAP
VMware
Oracle
Fortinet
PeopleCert
Eccouncil
HP
Palo Alto Networks
Adobe
ISC2
ServiceNow
Dell EMC
CheckPoint
Discount Deals
New
About
Contact
Login
Sign up
Home
Discussions
GAQM Discussions
Exam APM-001 Topic 7 Question 47 Discussion
GAQM Exam APM-001 Topic 7 Question 47 Discussion
Actual exam question for GAQM's APM-001 exam
Question #: 47
Topic #: 7
[All APM-001 Questions]
An output of Control Schedule is:
A
A project schedule network diagram
B
A schedule management plan
C
Schedule data
D
Schedule forecasts
Show Suggested Answer
Hide Answer
Suggested Answer:
D
by
Iluminada
at
Apr 08, 2024, 04:14 AM
Limited Time Offer
25%
Off
Get Premium APM-001 Questions as Interactive Web-Based Practice Test or PDF
Contribute your Thoughts:
Submit
Cancel
Francine
5 days ago
Haha, this question is like a game of 'guess the PMBOK term'! I'm going with B. Schedule management plan. Just to mix things up a bit.
upvoted
0
times
...
Virgina
7 days ago
Hmm, I was thinking it might be D. Schedule forecasts. But I guess C makes more sense as the actual output of the process.
upvoted
0
times
...
Helga
25 days ago
But don't we also get a project schedule network diagram as an output?
upvoted
0
times
...
Bonita
27 days ago
I disagree, I believe it is Schedule data.
upvoted
0
times
...
Laquita
1 months ago
I'm pretty sure the correct answer is C. Schedule data. That's the output of the Control Schedule process, right?
upvoted
0
times
Jules
2 days ago
Actually, the correct answer is A. A project schedule network diagram is an output of Control Schedule.
upvoted
0
times
...
Lorean
10 days ago
I think it might also be D. Schedule forecasts. That's important for monitoring and controlling the project schedule.
upvoted
0
times
...
Casandra
18 days ago
Yes, you are correct. Schedule data is indeed an output of the Control Schedule process.
upvoted
0
times
...
...
Helga
1 months ago
I think the output of Control Schedule is Schedule forecasts.
upvoted
0
times
...
Log in to Pass4Success
×
Sign in:
Forgot my password
Log in
Report Comment
×
Is the comment made by
USERNAME
spam or abusive?
Commenting
×
In order to participate in the comments you need to be logged-in.
You can
sign-up
or
login
Save
Cancel
az-700
pass4success
az-104
200-301
200-201
cissp
350-401
350-201
350-501
350-601
350-801
350-901
az-720
az-305
pl-300
Warning
: Cannot modify header information - headers already sent by (output started at /pass.php:70) in
/pass.php
on line
77
a
Francine
5 days agoVirgina
7 days agoHelga
25 days agoBonita
27 days agoLaquita
1 months agoJules
2 days agoLorean
10 days agoCasandra
18 days agoHelga
1 months ago