Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?
I'm going with A) Close Project or Phase. Updating those process assets sounds like something you'd do at the end of the project, not during the procurement process.
I think the answer is C) Control Procurements. The updates to organizational process assets are typically generated during the monitoring and controlling of the procurement process.