Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Jolene
2 months ago
I'm not sure, but I think it could also be D) Close Procurements, as it involves finalizing procurement activities.
upvoted 0 times
...
Dudley
2 months ago
I agree with Sean, because closing a project or phase usually involves updating process assets.
upvoted 0 times
...
Beth
2 months ago
Wait, are we talking about closing procurements or closing the bar tab? I'm always confused about which one comes first.
upvoted 0 times
Mila
24 days ago
D) Close Procurements
upvoted 0 times
...
Sharen
1 months ago
A) Close Project or Phase
upvoted 0 times
...
Tran
1 months ago
D) Close Procurements
upvoted 0 times
...
Tommy
1 months ago
A) Close Project or Phase
upvoted 0 times
...
...
Sean
2 months ago
I think the answer is A) Close Project or Phase.
upvoted 0 times
...
Tamekia
2 months ago
I'm going with A) Close Project or Phase. Updating those process assets sounds like something you'd do at the end of the project, not during the procurement process.
upvoted 0 times
...
Elroy
2 months ago
Nah, it's gotta be D) Close Procurements. That's where you wrap up the procurement activities and capture all the lessons learned, right?
upvoted 0 times
...
Elly
2 months ago
I'm not sure, but I think it could also be A) Close Project or Phase since it involves closing out the project.
upvoted 0 times
...
Alishia
2 months ago
Hmm, I'm not sure. Is it B) Conduct Procurements? That seems logical, since the procurement process would involve updating files and documentation.
upvoted 0 times
...
Franklyn
2 months ago
I think the answer is C) Control Procurements. The updates to organizational process assets are typically generated during the monitoring and controlling of the procurement process.
upvoted 0 times
Kirk
15 days ago
Definitely, it helps improve future procurement processes and overall project management.
upvoted 0 times
...
Carli
20 days ago
That makes sense, it's important to keep track of all the documentation and lessons learned during the procurement process.
upvoted 0 times
...
Beckie
27 days ago
So, the correct answer would be C) Control Procurements.
upvoted 0 times
...
Denae
1 months ago
I agree, the updates to organizational process assets are usually done during the monitoring and controlling of procurements.
upvoted 0 times
...
...
Gerry
2 months ago
I agree with Jacki, because closing procurements involves updating process assets.
upvoted 0 times
...
Jacki
2 months ago
I think the answer is D) Close Procurements.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77