Deal of The Day! Hurry Up, Grab the Special Discount - Save 25%
- Ends In
00:00:00
Coupon code:
SAVE25
X
Welcome to Pass4Success
Login
|
Sign up
-
Free
Preparation Discussions
Mail Us
support@pass4success.com
Location
PL
MENU
Home
Popular vendors
Salesforce
Microsoft
Nutanix
Cisco
Amazon
Google
CompTIA
SAP
VMware
Oracle
Fortinet
PeopleCert
Eccouncil
HP
Palo Alto Networks
Adobe
ISC2
ServiceNow
Dell EMC
CheckPoint
Discount Deals
New
About
Contact
Login
Sign up
Home
Discussions
GAQM Discussions
Exam APM-001 Topic 4 Question 70 Discussion
GAQM Exam APM-001 Topic 4 Question 70 Discussion
Actual exam question for GAQM's APM-001 exam
Question #: 70
Topic #: 4
[All APM-001 Questions]
What is the total float of the critical path?
A
Can be any number
B
Zero or positive
C
Zero or negative
D
Depends on the calendar
Show Suggested Answer
Hide Answer
Suggested Answer:
C
by
Leontine
at
Jan 15, 2025, 12:23 AM
Limited Time Offer
25%
Off
Get Premium APM-001 Questions as Interactive Web-Based Practice Test or PDF
Contribute your Thoughts:
Submit
Cancel
Jennie
29 days ago
I bet the person who wrote this question is a real 'float' enthusiast. Get it? Float? Haha!
upvoted
0
times
Katy
2 days ago
B) Zero or positive
upvoted
0
times
...
Marsha
4 days ago
A) Can be any number
upvoted
0
times
...
Johnetta
13 days ago
A) Can be any number
upvoted
0
times
...
...
Reid
2 months ago
If the total float of the critical path is negative, does that mean the project is already behind schedule? Yikes!
upvoted
0
times
Sonia
12 days ago
If the total float of the critical path is negative, does that mean the project is already behind schedule? Yikes!
upvoted
0
times
...
Marylyn
15 days ago
C) Zero or negative
upvoted
0
times
...
Lennie
1 months ago
B) Zero or positive
upvoted
0
times
...
Leonida
1 months ago
A) Can be any number
upvoted
0
times
...
...
Samira
2 months ago
I was tempted to choose option C, but then I remembered that the critical path has no slack, so the total float has to be zero.
upvoted
0
times
...
Beckie
2 months ago
I'm not a big fan of option A. The total float of the critical path definitely can't be 'any number'.
upvoted
0
times
Alease
28 days ago
Yeah, I think option B is the correct answer. Total float can't be negative.
upvoted
0
times
...
Samira
1 months ago
I agree, option A doesn't make sense. It has to be either zero or positive.
upvoted
0
times
...
...
Wilda
2 months ago
Hmm, I was thinking option D since the calendar can affect the total float, but zero or positive makes sense too.
upvoted
0
times
...
Rodolfo
2 months ago
I heard that the total float can be zero or negative if there are delays in the project.
upvoted
0
times
...
Cory
2 months ago
The total float of the critical path has to be zero or positive, so I'll go with option B.
upvoted
0
times
...
Kimberely
2 months ago
I believe it's either zero or positive, depending on the project schedule.
upvoted
0
times
...
Marvel
2 months ago
I think the total float of the critical path can be any number.
upvoted
0
times
...
Log in to Pass4Success
×
Sign in:
Forgot my password
Log in
Report Comment
×
Is the comment made by
USERNAME
spam or abusive?
Commenting
×
In order to participate in the comments you need to be logged-in.
You can
sign-up
or
login
Save
Cancel
az-700
pass4success
az-104
200-301
200-201
cissp
350-401
350-201
350-501
350-601
350-801
350-901
az-720
az-305
pl-300
Jennie
29 days agoKaty
2 days agoMarsha
4 days agoJohnetta
13 days agoReid
2 months agoSonia
12 days agoMarylyn
15 days agoLennie
1 months agoLeonida
1 months agoSamira
2 months agoBeckie
2 months agoAlease
28 days agoSamira
1 months agoWilda
2 months agoRodolfo
2 months agoCory
2 months agoKimberely
2 months agoMarvel
2 months ago