GAQM Exam APM-001 Topic 2 Question 29 Discussion

Actual exam question for GAQM's APM-001 exam
Question #: 29
Topic #: 2
[All APM-001 Questions]

The following is a network diagram for a project. The shortest non-critical path for the project is how many days in duration?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Zachary
26 days ago
Is it just me, or does this question look like it was designed to trick us? I'll have to channel my inner network ninja to crack this one. Hmm, I'm tempted to go with B) 12 days, but I'll leave the jokes to the experts.
upvoted 0 times
Marylou
7 days ago
I see where you're coming from, but I'm going with C) 14 days as my answer.
upvoted 0 times
...
Sharika
18 days ago
I think it's definitely a tricky question, but I'm leaning towards A) 10 days.
upvoted 0 times
...
...
Vincenza
1 months ago
Finally, a question I can sink my teeth into! Network analysis is my specialty. I'm going with D) 16 days, but I won't be surprised if someone comes up with a clever solution I overlooked.
upvoted 0 times
Marylou
7 days ago
I think the answer is B) 12 days.
upvoted 0 times
...
...
Amber
1 months ago
Ah, network diagrams, my old nemesis. Time to put on my thinking cap and get to work. I'm feeling confident in C) 14 days, but I'll keep an open mind in case I've missed something.
upvoted 0 times
...
Myong
2 months ago
I'm not sure, but I think it might be C) 14 days.
upvoted 0 times
...
Stephaine
2 months ago
This looks like a tricky one. I'll need to carefully analyze the network diagram to determine the shortest non-critical path. I'm leaning towards B) 12 days, but I'll double-check my work just to be sure.
upvoted 0 times
Rolf
11 days ago
Good idea, we don't want to make any mistakes on this one.
upvoted 0 times
...
Clare
1 months ago
Let's make sure to double-check our calculations before finalizing the answer.
upvoted 0 times
...
Major
1 months ago
I agree, option B) 12 seems to be the right choice.
upvoted 0 times
...
Ruthann
1 months ago
I think the shortest non-critical path is 12 days.
upvoted 0 times
...
...
Leila
2 months ago
I agree with Ressie, the shortest non-critical path is 12 days.
upvoted 0 times
...
Ressie
2 months ago
I think the answer is B) 12.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77
a