GAQM Exam APM-001 Topic 1 Question 50 Discussion

Actual exam question for GAQM's APM-001 exam
Question #: 50
Topic #: 1
[All APM-001 Questions]

Reserve analysis is a tool and technique used in which process?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Sylvie
14 days ago
Actually, reserve analysis is used in Plan Risk Responses to determine the amount of contingency reserves needed.
upvoted 0 times
...
Jaclyn
17 days ago
I disagree, I believe it is used in Control Risks.
upvoted 0 times
...
Sylvie
18 days ago
I think reserve analysis is used in Plan Risk Responses.
upvoted 0 times
...
Malinda
22 days ago
Hmm, I'm not sure. Let's discuss and figure it out together.
upvoted 0 times
...
Stefania
23 days ago
I believe it's actually used in Identify Risks.
upvoted 0 times
...
Malinda
25 days ago
I think reserve analysis is used in Plan Risk Responses.
upvoted 0 times
...