After the creation of the Release Plan, the Product Owner says:

Over the next four months with eights two-week Sprints we will complete exactly 240 Story Points of work.

The Scrum Master argues that the end date of the release can be positively or negatively impacted by three factors. Completed work is the first factor.

What are the other two factors?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Benton
6 days ago
Hmm, let me think... 'Fixed requirements and revised estimates'? Nah, that doesn't sound right. B) is the winner, no doubt about it. Gotta love these Scrum-tastic questions!
upvoted 0 times
...
Rodney
10 days ago
Ah, the age-old battle between Product Owners and Scrum Masters. 'Exactly 240 Story Points' - talk about setting the bar high! B) is the way to go here.
upvoted 0 times
...
Luther
14 days ago
I initially thought C) Fixed requirements and estimation mode, but then I realized that changed requirements is a key factor that can impact the release date. Good question!
upvoted 0 times
...
Becky
14 days ago
I believe option A) Changed requirements and estimation mode is the correct answer because these factors can cause delays in completing the work.
upvoted 0 times
...
Arlen
16 days ago
I agree with Lisha, changed requirements and estimation mode can definitely impact the end date of the release.
upvoted 0 times
...
Lisha
18 days ago
I think the other two factors are changed requirements and estimation mode.
upvoted 0 times
...
Regenia
18 days ago
The correct answer is B) Changed requirements and revised estimates. The Scrum Master is right - the end date can be impacted by both changed requirements and revised estimates, not just the completed work.
upvoted 0 times
Hyun
5 days ago
A) Changed requirements and estimation mode
upvoted 0 times
...
...