Exin Exam ASM Topic 8 Question 34 Discussion

Actual exam question for Exin's ASM exam
Question #: 34
Topic #: 8
[All ASM Questions]

Listed below are some risks and issues that might be encountered during the course of a project. Identify

which of the following are risks (not issues).

A) After extensive training, marketing representatives might still not be ready to take orders after the project is

launched.

B) The painting crew might be delayed due to heavy rain, which could negatively impact the project schedule.

C) Funding was not approved.

D) Requirements, as currently defined, are unclear.

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Alaine
2 months ago
I'd say the answer is A and B. The rain delay and lack of funding are textbook examples of project risks. Gotta love those trick questions, though!
upvoted 0 times
Daniela
4 days ago
I agree, A and B are definitely risks that could impact the project.
upvoted 0 times
...
Wendell
6 days ago
Absolutely, proactive risk management is key to project success.
upvoted 0 times
...
Elenor
7 days ago
I think we need to come up with a plan to mitigate these risks before they become bigger issues.
upvoted 0 times
...
Janessa
8 days ago
Yeah, the rain delay and lack of funding can really throw a wrench in things.
upvoted 0 times
...
Lai
15 days ago
I agree, A and B are definitely risks that could impact the project.
upvoted 0 times
...
...
Beckie
2 months ago
Haha, the marketing reps not being ready to take orders after training? That's just plain incompetence, not a risk! I'm going with C on this one.
upvoted 0 times
...
Carmela
2 months ago
I'm not sure about this one. Unclear requirements seem like an issue to me, but I guess it could also be considered a risk. Hmm, tough call.
upvoted 0 times
...
Kirk
2 months ago
I'm not sure, I think C could also be a risk.
upvoted 0 times
...
Sharan
2 months ago
I agree with Thea, A and B are definitely risks.
upvoted 0 times
...
Rosalyn
2 months ago
I think the answer is A and B. The painting crew delay due to rain and lack of funding approval are clearly risks, not issues.
upvoted 0 times
Beata
12 days ago
Correct, those are the risks identified in the options provided.
upvoted 0 times
...
Lindsey
27 days ago
So, we both think the answer is A and B then.
upvoted 0 times
...
Charlena
30 days ago
Yes, and the lack of funding approval is also a risk that could impact the project.
upvoted 0 times
...
Kathrine
1 months ago
Yes, those are risks because they could impact the project schedule and success.
upvoted 0 times
...
Marguerita
1 months ago
I agree, the painting crew delay and lack of funding approval are definitely risks.
upvoted 0 times
...
Glory
1 months ago
I agree, the painting crew delay due to rain is definitely a risk.
upvoted 0 times
...
...
Thea
2 months ago
I think the risks are A and B.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77
a