Exin Exam ASM Topic 10 Question 70 Discussion

Actual exam question for Exin's ASM exam
Question #: 70
Topic #: 10
[All ASM Questions]

A team has problems with product backlog management. The Developers do not always understand the ordering of the product backlog items. They sometimes find it difficult to understand the product backlog items and select the right items for the current sprint backlog

In this scenario which is a primary accountability of the Scrum Master?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Earlean
21 days ago
I believe the Scrum Master should also coach the customer to help them create clearer user stories, so that the Developers can better understand the product backlog items.
upvoted 0 times
...
Carmela
24 days ago
I agree with My. The Scrum Master should find ways to improve the management of the product backlog to help the team.
upvoted 0 times
...
My
26 days ago
I think the primary accountability of the Scrum Master is to help the Developers with ordering product backlog items.
upvoted 0 times
...