Near the end of a Sprint, the team realizes that they will not be able to complete the stories they had committed to.

What is the best course of action for the team?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Dexter
4 days ago
Ha! Adding more resources at the last minute? That's a recipe for disaster. B is the clear winner here.
upvoted 0 times
...
Hermila
17 days ago
Deciding on a new definition of 'done' for the Sprint Backlog Items might be a good way to ensure we can still deliver value.
upvoted 0 times
...
Joanna
18 days ago
I agree, B is the way to go. Trying to force the team to do more will just lead to burnout.
upvoted 0 times
Rikki
6 days ago
Let's ask the Product Owner to decide which stories can be delayed until the next Sprint.
upvoted 0 times
...
...
Valentine
19 days ago
B) Definitely the best option. Delaying stories to the next Sprint is the most flexible and transparent approach.
upvoted 0 times
...
Wilda
19 days ago
I think adding resources and team members to meet the goals of the current Sprint could help us catch up.
upvoted 0 times
...
Tenesha
21 days ago
We should ask the Product Owner to decide which stories can be delayed until the next Sprint.
upvoted 0 times
...