A project manager is overseeing the implementation of a major upgrade to a critical ERP system. The project sponsor is requiring that the upgrade should not exceed more than three hours of downtime for the implementation and validation in production. During cutover, the team runs into a validation issue after 2.5 hours, and the process is only 70% through the validation steps Which of the following actions should the project manager take?
Shasta
1 months agoLore
17 days agoCiara
29 days agoMeghann
1 months agoLeonor
1 months agoCrista
1 months agoKristel
2 months agoSolange
19 days agoSylvia
26 days agoDaren
1 months agoClare
1 months agoRenato
2 months agoDonette
2 months agoLouvenia
2 months agoCristen
1 months agoJerry
1 months agoKami
2 months agoSherman
2 months agoMari
2 months agoJeanice
2 months ago