A project manager is overseeing the implementation of a major upgrade to a critical ERP system. The project sponsor is requiring that the upgrade should not exceed more than three hours of downtime for the implementation and validation in production. During cutover, the team runs into a validation issue after 2.5 hours, and the process is only 70% through the validation steps Which of the following actions should the project manager take?
Kristel
6 days agoRenato
8 days agoDonette
9 days agoLouvenia
10 days agoKami
11 days agoSherman
13 days agoMari
19 days agoJeanice
23 days ago