A global shipping slowdown is causing critical raw materials needed for manufacturing to be delivered late. As a result, a project's production run will be delayed from the beginning.
Which of the following dependencies is most likely happening?
A Finish-to-Start dependency implies that a subsequent activity cannot start until a previous one finishes. In this scenario, the manufacturing process (subsequent activity) cannot begin until the critical raw materials (previous activity) have been delivered. This type of dependency is the most common in project schedules and is likely being affected by the global shipping slowdown, causing delays in the start of the project's production run.
Page
9 months agoClay
10 months agoLeonor
10 months agoIlona
10 months agoTawna
10 months agoEvangelina
10 months agoHobert
10 months agoAnnice
9 months agoTandra
9 months agoJaime
9 months agoPage
10 months agoAmos
10 months agoTeddy
9 months agoKristeen
9 months agoAshanti
9 months agoReid
9 months agoTroy
10 months agoMerlyn
10 months agoMargart
10 months ago