CompTIA Exam PK0-005 Topic 1 Question 44 Discussion

Actual exam question for CompTIA's PK0-005 exam
Question #: 44
Topic #: 1
[All PK0-005 Questions]

During the execution phase of a project, team members have been constantly disagreeing about the tasks they have been assigned. Which of the following is most likely the reason they are disagreeing?

Show Suggested Answer Hide Answer
Suggested Answer: B

A RACI matrix clarifies roles and responsibilities for tasks, reducing confusion and disagreements among team members. Missing or incomplete information in the RACI matrix could lead to disputes, as it is a key tool for accountability in project management per CompTIA Project+.


Contribute your Thoughts:

Valentin
15 days ago
Hold up, is this a trick question? I bet they're all disagreeing because they haven't had their coffee yet. That's the real reason behind any team conflict!
upvoted 0 times
...
Dannie
20 days ago
I'm going with C. New knowledge bases can throw a wrench in the works, especially if the team isn't properly trained on them.
upvoted 0 times
...
Kathrine
23 days ago
Hmm, I'm not sure. Could it be D? If there aren't enough team touch points, communication breakdowns are bound to happen.
upvoted 0 times
...
Arthur
1 months ago
But what if new knowledge bases were introduced? Could that also cause disagreements among team members?
upvoted 0 times
...
Jade
1 months ago
I think it's B. The RACI matrix is crucial for defining roles and responsibilities, and if that information is missing, it's no wonder the team members are disagreeing.
upvoted 0 times
Lacey
29 days ago
A) Some work packages are missing from the WBS.
upvoted 0 times
...
...
Jestine
1 months ago
I agree with Irma, if the work packages are not clearly defined, it can lead to confusion and disagreements among team members.
upvoted 0 times
...
Irma
2 months ago
I think the reason they are disagreeing is because some work packages are missing from the WBS.
upvoted 0 times
...

Save Cancel