Joanne is preparing a contract for the construction of a large shopping center.
The project includes 52 retail units, several restaurants, and a parking facility.
Joanne's company has contracted Construct Ltd under a Turnkey project.
She is using a Gantt chart as a schedule in the contract.
Q: What type of payment mechanism is being used in this contract?
Answer Options:
The correct answer is Activity Schedule (p.60). A Gantt chart is a time-based project planning tool, typically used in Activity Schedule contracts, where payments are tied to the completion of specific tasks. Other payment methods, such as Fixed Lump Sum and Bill of Quantity, do not rely on this approach. [P.60]
Maile
24 hours agoAleta
5 days agoJohnson
2 days agoMartha
18 days agoJeffrey
24 days agoLouisa
1 months agoVanesa
1 months agoDorethea
4 days agoGertude
12 days agoTayna
13 days agoMalinda
1 months agoCharolette
1 months agoFannie
5 days agoJospeh
22 days agoMalcom
1 months agoJenelle
2 months agoJoye
16 days agoAudry
17 days agoEmmanuel
22 days ago