Independence Day Deal! Unlock 25% OFF Today – Limited-Time Offer - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

CIPS Exam L4M7 Topic 3 Question 23 Discussion

Actual exam question for CIPS's L4M7 exam
Question #: 23
Topic #: 3
[All L4M7 Questions]

MRP system is the most suitable IT system to manage which type of items?

Show Suggested Answer Hide Answer
Suggested Answer: A, B

The most common subjective forecasting techniques include the following:

- Market surveys

- Employee surveys

- Expert knowledge (Delphi method is a method using expert knowledge)

- Test marketing

Cycle counting is a periodic analysis of inventory in a storage location which is conducted through the counting of samples instead of physically counting the entire inventory available, so as to quickly have an accurate estimate of the inventory available without causing a stop to the day to day working as is the case with physically counting every unit.

The Pareto principle (also known as the 80/20 rule, the law of the vital few, or the principle of fac-tor sparsity) states that, for many events, roughly 80% of the effects come from 20% of the causes.

Weighted moving averages assign a heavier weighting to more current data points since they are more relevant than data points in the distant past. The sum of the weighting should add up to 1 (or 100 percent).


LO 2, AC 2.3

Contribute your Thoughts:

Niesha
29 days ago
Gotta be option A, my friends. Dependent demand is the bread and butter of MRP. Anything else and you're just asking for trouble.
upvoted 0 times
...
Shawna
1 months ago
Ha! Fast moving components? Sounds like someone's trying to trick us. MRP is all about planning and control, not the latest gadgets and gizmos.
upvoted 0 times
Bulah
13 days ago
A) Dependent demand
upvoted 0 times
...
...
Joye
2 months ago
I'm not so sure about that. Isn't MRP more suited for things like finished goods with independent demand? Construction projects seem like a whole different animal.
upvoted 0 times
Geraldo
10 days ago
D) Fast moving components
upvoted 0 times
...
Annelle
12 days ago
I agree, MRP systems are typically used for managing items with independent demand.
upvoted 0 times
...
Evelynn
14 days ago
C) Independent demand
upvoted 0 times
...
Carissa
17 days ago
A) Dependent demand
upvoted 0 times
...
...
Kirk
2 months ago
I'm not sure about that. I think the answer might be C) Independent demand.
upvoted 0 times
...
Bette
2 months ago
I agree with Maybelle. MRP system is designed to manage dependent demand items.
upvoted 0 times
...
Whitney
2 months ago
MRP is definitely the way to go for dependent demand items. Anything with a clear relationship to other items in the production process is a perfect fit.
upvoted 0 times
Xenia
18 days ago
C) Independent demand
upvoted 0 times
...
Timmy
21 days ago
A) Dependent demand
upvoted 0 times
...
...
Maybelle
2 months ago
I think the answer is A) Dependent demand.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  