GSC Ltd is a manufacturer of car parts. To accommodate growing demands of electric cars, the company is developing a new component which requires different type of steel. The project team estimates that the component will be ready for production in 1.5 years. Until then, they need to keep the production busy.
After checking the inventory records, the production team sees that the company has 3 months of stock. The lead time for each batch is two months. Which of the following should be a priority ac-tion of the company?
Writing a specification and then procuring and using the product or service has a number of stages. The further on in the process you are, the less potential there is for cost reductions. Therefore, opportunities for cost reduction will be greatest in the two first stages: planning stage and pre-design stage.
LO 3, AC 3.1
Deonna
1 months agoJulio
2 months agoBernardo
24 days agoClaudio
1 months agoJeannine
1 months agoShenika
2 months agoAnjelica
13 days agoMagnolia
17 days agoDorinda
23 days agoAdela
24 days agoDannette
2 months agoKati
1 months agoJettie
1 months agoTalia
2 months agoAileen
2 months agoTony
3 months agoMee
3 months ago