Actual exam question for CIPS's L4M2 exam
Question #: 24
Topic #: 10
[All L4M2 Questions]

A consulting firm in London had previously had static budgets. They were set once and locked in for the year. This resulted in departments meeting their budgets early and doing virtually nothing the rest of the accounting period. To address this imbalance, the company tossed out the static budget and developed a new one for each department of the next 18 months. And each month, real sales figures are analyzed against the plan and the budget is adjusted accordingly. Then the company adds another month into the budgeting plan. What type of budget this company is using?

Show Suggested Answer Hide Answer
Suggested Answer: B

Those items make up small portion of spend and the supply risk is low. So it is tactical item according to Kraljic portfolio matrix. Procurement should bundle these items into larger contracts, simplify procurement process.

LO 2, AC 2.1


Contribute your Thoughts:

Tom
17 days ago
I'm not sure, but I think a rolling budget is more flexible and helps prevent departments from just sitting on their budgets.
upvoted 0 times
...
Dana
19 days ago
I agree with Sabine. A rolling budget allows for adjustments based on real sales figures.
upvoted 0 times
...
Sabine
20 days ago
I think the company is using a rolling budget.
upvoted 0 times
...