To which technique for dealing with risk and uncertainty do ALL of the following statements apply?
* It requires that only one factor is considered at a time.
* It identifies areas which are crucial to a project, which can then be monitored if the project is chosen.
* It does not provide an indication of the likelihood of any change in the factors.
* Following the calculation, it requires the exercising of judgement to decide whether to accept or reject a project.