CIMA Exam CIMAPRA19-P03-1 Topic 6 Question 62 Discussion

Actual exam question for CIMA's CIMAPRA19-P03-1 exam
Question #: 62
Topic #: 6
[All CIMAPRA19-P03-1 Questions]

W is a construction company which undertakes large projects for governments and other clients worldwide. Following extensive tendering processes, contracts are issued for successful tenders,and projects typically take three to five years to complete. Contracts are normally fixed-price and many have considerable penalty clauses.

Which of the following would beappropriate policies and controls for W to implement?

Show Suggested Answer Hide Answer
Suggested Answer: B, C, E

Contribute your Thoughts:

Glen
29 days ago
I hope the project steering committee has snacks during those status meetings. Gotta keep the team's energy up for all those construction projects!
upvoted 0 times
...
Nadine
30 days ago
Regular project status updates are essential for effective oversight. Option F is a practical way to keep the leadership informed and on top of things.
upvoted 0 times
...
Delila
1 months ago
Good point. Precise contract wording is important to avoid ambiguity and disputes. Option E is a smart way to protect the company's interests.
upvoted 0 times
Justine
10 days ago
A) Unsuccessful tenders should be analysed to establish the cause of them failing to be awarded the work and help to avoid future failures.
upvoted 0 times
...
...
Cheryl
1 months ago
Hmm, Option D seems a bit risky. Committing to the absolute lowest price and shortest time might jeopardize quality and lead to penalties. I'd be cautious with that one.
upvoted 0 times
Dong
23 hours ago
E) Contract terms should be worded precisely so that additional work is not deemed to form part of the contract.
upvoted 0 times
...
Matilda
3 days ago
B) Ensuring a consistent separation of duties between those involved in the preparation of tenders and those involved in the planning of projects.
upvoted 0 times
...
Yuonne
13 days ago
A) Unsuccessful tenders should be analysed to establish the cause of them failing to be awarded the work and help to avoid future failures.
upvoted 0 times
...
...
Art
2 months ago
Paying at least the legal minimum wage is a must. Option C is a no-brainer to ensure compliance and treat workers fairly.
upvoted 0 times
Gertude
4 days ago
F) The project steering committee and project board should receive regular project status reports.
upvoted 0 times
...
Minna
6 days ago
C) Ensuring that the minimum legal wage is paid to all workers on the construction sites.
upvoted 0 times
...
Shanda
13 days ago
B) Ensuring a consistent separation of duties between those involved in the preparation of tenders and those involved in the planning of projects.
upvoted 0 times
...
Art
2 months ago
A) Unsuccessful tenders should be analysed to establish the cause of them failing to be awarded the work and help to avoid future failures.
upvoted 0 times
...
...
Bettina
2 months ago
Absolutely, separation of duties is crucial to ensure proper checks and balances. Option B is a solid choice for maintaining control and accountability.
upvoted 0 times
Valentin
1 months ago
User 2: Definitely, it helps prevent any conflicts of interest.
upvoted 0 times
...
Cyril
1 months ago
User 1: I agree, separation of duties is key for transparency.
upvoted 0 times
...
...
Avery
2 months ago
I believe option B is also essential to maintain transparency and prevent conflicts of interest.
upvoted 0 times
...
Daron
2 months ago
Analyzing unsuccessful tenders is a great idea to improve future bids. I like how option A focuses on understanding the reasons behind the failures.
upvoted 0 times
...
Avery
2 months ago
I agree with you, Vernice. It's crucial to learn from past mistakes.
upvoted 0 times
...
Vernice
2 months ago
I think option A is important to analyze why tenders fail.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77