Having carried out a full capital appraisal for a construction project, HCompanyhasapproved the project with initial outflows of $6,000,000 anda net present value of $1,200,000.
The implementation phase has been commenced with 25% of the costs already committed.However whenthe ground was opened, an underground waterway was revealedwhich will need to be diverted if the project is to proceed. Work to carry out this diversion has been estimated at $1,300,000.
Which of the following factors will define whether the project should go ahead or not?