CIMA Exam CIMAPRA19-E02-1 Topic 5 Question 64 Discussion

Actual exam question for CIMA's CIMAPRA19-E02-1 exam
Question #: 64
Topic #: 5
[All CIMAPRA19-E02-1 Questions]

The difference between the latest event time and the earliest event time in a project network analysis is referred to as:

Show Suggested Answer Hide Answer
Suggested Answer: A, B

Contribute your Thoughts:

Dusti
10 days ago
I'm not sure, but I think it could also be C) Critical Path, as it represents the longest path in the project.
upvoted 0 times
...
Shizue
12 days ago
I agree with Darnell, because float represents the flexibility in scheduling non-critical activities.
upvoted 0 times
...
Kristel
12 days ago
I think the answer is B. Float, as it represents the time difference between the latest and earliest event times in the project network analysis.
upvoted 0 times
...
Darnell
19 days ago
I think the answer is B) Float.
upvoted 0 times
...