CIMA Exam CIMAPRA19-E02-1 Topic 5 Question 64 Discussion

Actual exam question for CIMA's CIMAPRA19-E02-1 exam
Question #: 64
Topic #: 5
[All CIMAPRA19-E02-1 Questions]

The difference between the latest event time and the earliest event time in a project network analysis is referred to as:

Show Suggested Answer Hide Answer
Suggested Answer: A, B

Contribute your Thoughts:

Dante
1 months ago
This is a no-brainer! The answer is B. Float, just like the air I'm breathing right now. Unless, of course, the project manager has been secretly inflating the tires on the critical path...
upvoted 0 times
...
Ciara
1 months ago
Hmm, is the answer D. Node? Because the Ciarant times are literally the nodes in the network diagram, right? No? Okay, I'll go with B. Float then.
upvoted 0 times
...
Rikki
1 months ago
A. Critical Activity? Not even close! That's a single activity on the critical path, not the difference between the event times. B. Float is the way to go here.
upvoted 0 times
...
Catherin
1 months ago
D. Node? Really? That's like saying the difference between the latest and earliest event times is a point on the network diagram. Clearly, the answer is B. Float.
upvoted 0 times
Cecilia
1 days ago
C) Critical Path
upvoted 0 times
...
Merlyn
7 days ago
B) Float
upvoted 0 times
...
Magnolia
18 days ago
A) Critical Activity
upvoted 0 times
...
...
Aileen
1 months ago
C. Critical Path seems like the correct answer to me. It represents the sequence of activities that determine the overall duration of the project.
upvoted 0 times
Ronna
2 days ago
Yes, the Critical Path is the sequence of activities that determine the project duration.
upvoted 0 times
...
Jeanice
6 days ago
C) Critical Path
upvoted 0 times
...
Rachael
12 days ago
B) Float
upvoted 0 times
...
Glory
16 days ago
I think you're right, the Critical Path is the correct answer.
upvoted 0 times
...
Ricarda
1 months ago
A) Critical Activity
upvoted 0 times
...
...
Dusti
2 months ago
I'm not sure, but I think it could also be C) Critical Path, as it represents the longest path in the project.
upvoted 0 times
...
Shizue
2 months ago
I agree with Darnell, because float represents the flexibility in scheduling non-critical activities.
upvoted 0 times
...
Kristel
2 months ago
I think the answer is B. Float, as it represents the time difference between the latest and earliest event times in the project network analysis.
upvoted 0 times
Arthur
27 days ago
Yes, float is the term used to describe the time difference between the latest and earliest event times.
upvoted 0 times
...
Annabelle
1 months ago
I agree, the float is the correct answer.
upvoted 0 times
...
...
Darnell
2 months ago
I think the answer is B) Float.
upvoted 0 times
...

Save Cancel