U is a retail chain of fashionoutlets. It has invested in a new logistics system to control the movement of stock between its warehouses and high street retail outlets.

The project to develop and install the new systemwas significantly over budget and very late. Now, only three months after the new system has been installed, it is apparent that the project has not delivered its objectives. Many retail managers are complaining that they are not receiving the correct stock to sell. A meeting between the project team and project sponsor ended with everyone blaming each other.

Which of the followingstatementsshowhowthe use of PRINCE2 might have reduced the problems encountered?

Select ALL that apply.

Show Suggested Answer Hide Answer
Suggested Answer: A, B, C

Contribute your Thoughts:

Mitsue
1 months ago
PRINCE2 training? Who needs that? I'm a natural-born project manager. I could have fixed this mess with my eyes closed. *laughs sarcastically*
upvoted 0 times
...
Mattie
1 months ago
Quality assurance and testing should have been a top priority. Rushing to finish the project as soon as possible is a recipe for disaster. PRINCE2 emphasizes the importance of validation and acceptance.
upvoted 0 times
...
Abraham
1 months ago
An organizational structure with clear roles and responsibilities could have prevented the blame game between the project team and sponsor. PRINCE2 is all about setting up the right governance.
upvoted 0 times
Maira
3 days ago
C) An emphasis on quality assurance and testing.
upvoted 0 times
...
Lyndia
7 days ago
B) An organisation structure setting out clear roles.
upvoted 0 times
...
Oren
29 days ago
A) A focus on the business case of the project.
upvoted 0 times
...
...
Princess
2 months ago
I believe option C would have also been beneficial to ensure quality assurance and testing.
upvoted 0 times
...
Annice
2 months ago
I agree with Lorrie, having a focus on the business case is crucial for project success.
upvoted 0 times
...
Lorrie
2 months ago
I think option A would have helped with the project's success.
upvoted 0 times
...
Raymon
2 months ago
A focus on the business case would have been crucial to ensure the project aligned with the company's objectives. Without that, it's no wonder the project went over budget and failed to deliver.
upvoted 0 times
Talia
16 days ago
Finishing as soon as possible may have led to rushed work and more mistakes.
upvoted 0 times
...
Eugene
26 days ago
Quality assurance and testing would have caught any issues with the new system before it was fully implemented.
upvoted 0 times
...
Aliza
1 months ago
Having clear roles in the organization structure could have prevented the blame game at the meeting.
upvoted 0 times
...
Celeste
1 months ago
C) An emphasis on quality assurance and testing.
upvoted 0 times
...
Justine
1 months ago
Yes, focusing on the business case would have helped keep the project on track.
upvoted 0 times
...
Buck
2 months ago
A) A focus on the business case of the project.
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77