CIMA Exam CIMAPRA19-E02-1 Topic 2 Question 100 Discussion

Actual exam question for CIMA's CIMAPRA19-E02-1 exam
Question #: 100
Topic #: 2
[All CIMAPRA19-E02-1 Questions]

Many companies use Critical Path Analysis (CPA)to manage projects.

Which TWO of the options belowcould beidentified from a CPA diagram?

Show Suggested Answer Hide Answer
Suggested Answer: C, E

Contribute your Thoughts:

Carlton
4 days ago
B and D seem like the correct answers to me. The critical path should give us information about resource usage and the time for each activity.
upvoted 0 times
...
Sheron
5 days ago
I think A and D are the right answers. The critical path tells us the activities that need to be done in order, and the probable time for each activity.
upvoted 0 times
...
Mabel
8 days ago
A and C are definitely the correct answers. The critical path shows the activities that are essential for the project to be completed on time.
upvoted 0 times
...
Herminia
10 days ago
I'm not sure about C, but I definitely think A and D are important for a CPA diagram.
upvoted 0 times
...
Matt
12 days ago
I agree with Scot. A and C make sense because they are crucial for project management.
upvoted 0 times
...
Scot
25 days ago
I think A and C could be identified from a CPA diagram.
upvoted 0 times
...

Save Cancel