CIMA Exam CIMAPRA17-BA2-1 Topic 1 Question 74 Discussion

Actual exam question for CIMA's CIMAPRA17-BA2-1 exam
Question #: 74
Topic #: 1
[All CIMAPRA17-BA2-1 Questions]

The standard labour hours for all products manufactured by a company include an allowance for idle time. Idle time is budgeted to be 5% of total hours worked. Each unit of product G requires an input of 9.5 active labour hours. The labour rate is $12 per hour.

The standard labour cost shown on the standard cost card for one unit of product G will be

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Lashaun
1 months ago
Idle time, eh? I bet the answer is something like 'the cost of doing nothing'... *laughs*
upvoted 0 times
...
Nicolette
1 months ago
Ah, the old 'include the idle time' trick. Gotta watch out for that one. *chuckles*
upvoted 0 times
Bethanie
6 days ago
A) $10.00
upvoted 0 times
...
Eric
6 days ago
B) $114.00
upvoted 0 times
...
Chandra
9 days ago
A) $10.00
upvoted 0 times
...
...
Celestina
1 months ago
I love these questions where you have to think it through step-by-step. It's like a little puzzle, you know?
upvoted 0 times
Ashley
1 days ago
C) $119.70
upvoted 0 times
...
Ena
25 days ago
B) $114.00
upvoted 0 times
...
Anika
1 months ago
A) $10.00
upvoted 0 times
...
...
Art
2 months ago
Wait, do we have to include the idle time in the standard labor cost? That's a tricky one.
upvoted 0 times
Ernest
25 days ago
C) $119.70
upvoted 0 times
...
Jeff
26 days ago
B) $114.00
upvoted 0 times
...
Nickole
1 months ago
A) $10.00
upvoted 0 times
...
...
Jennie
2 months ago
Hmm, let's see... 9.5 active labor hours, 5% idle time, and $12 per hour. Seems like a straightforward calculation to me.
upvoted 0 times
Roosevelt
4 days ago
B) $114.00
upvoted 0 times
...
Iola
13 days ago
That's correct. The idle time is already factored into the standard labor cost.
upvoted 0 times
...
Becky
1 months ago
A) $10.00
upvoted 0 times
...
...
Edward
2 months ago
I'm not sure about this one. Can someone explain why the answer is C) $119.70?
upvoted 0 times
...
Gianna
2 months ago
I agree with Sherill. The idle time is already included in the standard labour cost, so it should be C) $119.70.
upvoted 0 times
...
Sherill
2 months ago
I think the answer is C) $119.70.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77