BICSI Exam RCDDv14.1 Topic 5 Question 54 Discussion

Actual exam question for BICSI's RCDDv14.1 exam
Question #: 54
Topic #: 5
[All RCDDv14.1 Questions]

A program is in its execution phase when a component project manager suggests a potential change that could increase the financial benefit of the program. The program manager is hesitant to submit a change request, as it would extend the program schedule and require a scope change.

To whom should the change request be presented?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Mirta
1 days ago
I see your point, Mattie. It's important to consider the program customer's perspective too. Maybe the change request should be presented to both the program governance board and the program customer for their input.
upvoted 0 times
...
Mattie
2 days ago
But what if the program customer has a say in the financial benefit of the program? Shouldn't the change request be presented to them as well?
upvoted 0 times
...
Selene
13 days ago
I agree with Jennie. The program governance board is responsible for overseeing the program and making decisions like this.
upvoted 0 times
...
France
19 days ago
Wow, this is a real brain-teaser! I bet the program manager is wishing they had a crystal ball to see the future and make the right call. Maybe they should just roll a dice and see what happens!
upvoted 0 times
Curt
2 days ago
C) The program management office (PMO)
upvoted 0 times
...
Dorothy
5 days ago
B) The program customer
upvoted 0 times
...
Verdell
9 days ago
C) The program management office (PMO)
upvoted 0 times
...
Mike
10 days ago
A) The program governance board
upvoted 0 times
...
Barb
17 days ago
A) The program governance board
upvoted 0 times
...
...
Carin
1 months ago
This is a tough one, but I reckon the protect governance board would be the best choice. After all, they're the ones in charge of the program's governance, right?
upvoted 0 times
Kathrine
17 days ago
B) The program customer
upvoted 0 times
...
Annette
18 days ago
A) The program governance board
upvoted 0 times
...
...
Cassi
1 months ago
Hold on, isn't the PMO responsible for managing changes to the program? I'd say that's the way to go.
upvoted 0 times
...
Lorrie
1 months ago
Hmm, I'm not so sure. The program customer might be a better option since they're the one who would ultimately benefit from the increased financial gain.
upvoted 0 times
Tijuana
8 days ago
C) The program management office (PMO)
upvoted 0 times
...
Lavonna
10 days ago
B) The program customer
upvoted 0 times
...
Jeniffer
18 days ago
A) The program governance board
upvoted 0 times
...
...
Jennie
1 months ago
I think the change request should be presented to the program governance board.
upvoted 0 times
...
Ressie
2 months ago
I think the program governance board would be the appropriate body to present the change request to. They have the authority to make decisions that impact the program's scope, schedule, and budget.
upvoted 0 times
Tayna
4 days ago
A) The program governance board
upvoted 0 times
...
Laila
5 days ago
C) The program management office (PMO)
upvoted 0 times
...
Myong
5 days ago
I think the PMO would also be a good choice, as they can provide guidance on how to proceed with the change request.
upvoted 0 times
...
Kirk
6 days ago
C) The program management office (PMO)
upvoted 0 times
...
Richelle
10 days ago
I agree, the program governance board has the authority to approve changes that impact the program.
upvoted 0 times
...
Clorinda
13 days ago
A) The program governance board
upvoted 0 times
...
Armanda
1 months ago
I agree, they are the ones who can make decisions regarding the program's scope and schedule.
upvoted 0 times
...
Stefan
1 months ago
A) The program governance board
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77