BICSI Exam RCDDv14.1 Topic 4 Question 48 Discussion

Actual exam question for BICSI's RCDDv14.1 exam
Question #: 48
Topic #: 4
[All RCDDv14.1 Questions]

A key stakeholder's requirement contradicts the organization's strategic objectives. The program manager meets with the stakeholder but is unable to reach a compromise on the requirement

What should the program manager do first?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Tomas
5 days ago
You know, if the stakeholder was a cat, the program manager could just offer them some catnip and they'd forget all about their requirement. Meow-sic to my ears!
upvoted 0 times
...
Reita
10 days ago
Hold on, isn't the program sponsor supposed to be the one who's supposed to make the tough decisions? Why is the program manager even meeting with the stakeholder in the first place? This is a classic case of passing the buck!
upvoted 0 times
...
Marsha
23 days ago
I disagree. Meeting with the program management office to update the benefits management plan (Option A) would be a more proactive approach to addressing this issue.
upvoted 0 times
...
Queenie
26 days ago
I believe meeting with the customer to determine the validity of the stakeholder's requirement is also important.
upvoted 0 times
...
Jerry
26 days ago
Option C seems like the best choice here. The program sponsor should be able to provide guidance on how to resolve this conflict between the stakeholder's requirement and the organization's strategic objectives.
upvoted 0 times
Nieves
11 days ago
That's true, getting clarification from the strategic planning committee could also be beneficial.
upvoted 0 times
...
Candra
13 days ago
But wouldn't it also be helpful to update the benefits management plan with the program management office?
upvoted 0 times
...
Olive
14 days ago
I agree, meeting with the program sponsor is a good first step.
upvoted 0 times
...
...
Markus
1 months ago
I agree with Oliva. The program sponsor can help address the issue.
upvoted 0 times
...
Oliva
1 months ago
I think the program manager should meet with the program sponsor first.
upvoted 0 times
...