BICSI Exam RCDDv14.1 Topic 4 Question 36 Discussion

Actual exam question for BICSI's RCDDv14.1 exam
Question #: 36
Topic #: 4
[All RCDDv14.1 Questions]

A program is completed and the expected benefits are realized Before executing the transition and closing of the program, what should the program manager do?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Alonzo
7 days ago
The program manager should also treat the team to a pizza party. They've worked hard, and a little celebration is well-deserved!
upvoted 0 times
...
Holley
8 days ago
Performing administrative and PMIS closure activities is the perfect way to wrap things up. Tying up all the loose ends is key for a smooth transition.
upvoted 0 times
...
Tula
9 days ago
I think obtaining approval from the program governance board is essential. It ensures we have the green light to move forward with program closure activities.
upvoted 0 times
...
Jacklyn
15 days ago
Archiving documents and lessons learned is crucial for institutional knowledge. We can learn from past experiences to improve future programs.
upvoted 0 times
...
Phillip
2 months ago
Creating a final program report seems like the logical first step. It's a great way to document the project's journey and share key insights with stakeholders.
upvoted 0 times
Emerson
8 days ago
D) Perform administrative and program management information system (PMIS) closure activities.
upvoted 0 times
...
Kenneth
12 days ago
C) Obtain approval from the program governance board to initiate program closure activities
upvoted 0 times
...
Jackie
17 days ago
B) Archive documents and lessons learned
upvoted 0 times
...
Trina
23 days ago
A) Create a final program report.
upvoted 0 times
...
...
Micheal
2 months ago
Yes, creating a final program report can help in evaluating the success of the program and communicating the results to stakeholders.
upvoted 0 times
...
Christiane
2 months ago
I agree with that. It's important to document the outcomes and benefits.
upvoted 0 times
...
James
2 months ago
I think the program manager should create a final program report.
upvoted 0 times
...