BICSI Exam RCDDv14.1 Topic 1 Question 29 Discussion

Actual exam question for BICSI's RCDDv14.1 exam
Question #: 29
Topic #: 1
[All RCDDv14.1 Questions]

Which two of the following items should be considered for inclusion in a comprehensive working outline of a SoW? (Select two options.)

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Hmm, I would have thought legal matters and financial considerations are also crucial for a comprehensive SoW. Can't have any surprises down the line, right?
upvoted 0 times
...
Louis
7 days ago
I would also add Financial matters. It's important to have a clear budget plan.
upvoted 0 times
...
Reena
8 days ago
I agree with Evangelina. Those two are crucial for a comprehensive SoW outline.
upvoted 0 times
...
Evangelina
10 days ago
I think Schedule and Technical considerations should be included.
upvoted 0 times
...
Elinore
12 days ago
I would also add Financial matters because they are important for project planning and budgeting.
upvoted 0 times
...
Helaine
13 days ago
I agree with Kara. Those two are crucial for a comprehensive SoW outline.
upvoted 0 times
...
Louann
15 days ago
Schedule and technical considerations are definitely the key items to include in a SoW outline. The others are important, but more for the overall project management rather than the statement of work itself.
upvoted 0 times
...
Kara
24 days ago
I think Schedule and Contract administration should be included.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77