BICSI Exam RCDDv14.1 Topic 1 Question 21 Discussion

Actual exam question for BICSI's RCDDv14.1 exam
Question #: 21
Topic #: 1
[All RCDDv14.1 Questions]

To increase its presence and promote its products and services in new markets, a company begins to implement its new business strategy. The company's CEO endorses a new program to promote and support this strategy However before the program is formally initialed, this strategy must be aligned with the organization's strategic goals and objectives.

What should the program manager develop first?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Amber
1 months ago
You know, I heard the CEO is offering a prize for the first person to develop a 'program risk management plan' bingo card. Talk about an incentive to get it right!
upvoted 0 times
...
Jacquline
1 months ago
Ah yes, the age-old question of which risk-related document to develop first. I say we just roll the dice and see what happens!
upvoted 0 times
...
Ciara
1 months ago
Seriously? You all are missing the obvious - the program manager should develop a risk threshold. Gotta know what level of risk the company is willing to accept before anything else.
upvoted 0 times
...
Marjory
1 months ago
Hold on, I think the risk and issue governance forum is the way to go. That way, you can get everyone on the same page before finalizing the plan.
upvoted 0 times
...
Leigha
1 months ago
I disagree, I think the program manager should develop the resource management plan first. You can't plan for risks without knowing what resources you have to work with.
upvoted 0 times
...
Avery
1 months ago
The correct answer is B) Program risk management plan. This is the first step to ensure the new program aligns with the organization's strategic goals and objectives.
upvoted 0 times
Celestina
10 days ago
A: Once we have that in place, we can move forward with implementing the new business strategy.
upvoted 0 times
...
Eliz
18 days ago
B: That's right, it's important to align the new program with the organization's strategic goals.
upvoted 0 times
...
Arleen
1 months ago
A: We need to develop the program risk management plan first.
upvoted 0 times
...
...
Nettie
2 months ago
I think the program manager should also consider developing the program resource management plan to ensure resources are allocated effectively.
upvoted 0 times
...
Emerson
2 months ago
I agree with Phyliss. Developing the risk management plan will help identify potential risks and how to mitigate them.
upvoted 0 times
...
Phyliss
2 months ago
I think the program manager should develop the program risk management plan first.
upvoted 0 times
...
Jeanice
2 months ago
I think the program's risk threshold should be developed first to set the boundaries for risk tolerance.
upvoted 0 times
...
Evangelina
3 months ago
I agree with Samira. Developing the risk management plan will help identify potential risks and how to mitigate them.
upvoted 0 times
...
Samira
3 months ago
I think the program manager should develop the program risk management plan first.
upvoted 0 times
...

Save Cancel