BCS Exam ISEB-PM1 Topic 10 Question 70 Discussion

Actual exam question for BCS's ISEB-PM1 exam
Question #: 70
Topic #: 10
[All ISEB-PM1 Questions]

A contract management plan is a subsidiary of what other type of plan?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Yuette
2 days ago
I think the answer is B) Project management plan
upvoted 0 times
...
Valentine
24 days ago
I was a little unsure at first, but now that I think about it, the contract management plan has to be a part of the project management plan. I mean, how else would you manage all the contracts and agreements involved in a project?
upvoted 0 times
...
Audrie
26 days ago
I agree with Hubert. The contract management plan is part of the broader project management plan, which outlines all the processes and procedures for managing the project, including contracts and agreements.
upvoted 0 times
...
Lynelle
26 days ago
Hmm, I'm not sure about those other options. A resource plan or a cost control plan don't seem directly related to managing contracts. The project management plan just makes the most sense to me.
upvoted 0 times
...
Hubert
27 days ago
Hmm, this seems like a pretty straightforward question. I'm fairly confident that the correct answer is B) Project management plan. A contract management plan is definitely a subsidiary of the overall project management plan.
upvoted 0 times
...
Gearldine
27 days ago
Yeah, that's what I was thinking too. The contract management plan is probably a sub-plan that falls under the project management plan. It's all about managing the contracts associated with the project.
upvoted 0 times
...
Carma
27 days ago
I agree with you all, but I'm also curious about the other options. Could the contract management plan be a subsidiary of a resource plan or a cost control plan? Those seem plausible too.
upvoted 0 times
...
Judy
28 days ago
I was thinking the same thing, Mozell. It just makes sense that the contract management plan would be part of the broader project management plan, right?
upvoted 0 times
...
Mozell
1 months ago
Okay, let's see. A contract management plan deals with the management of contracts, so it's probably related to the overall project management plan. That's my best guess.
upvoted 0 times
...
Alisha
1 months ago
Hmm, a contract management plan as a subsidiary of another plan? This seems like a tricky one. I'm going to have to think this through carefully.
upvoted 0 times
...