BCS Exam PC-BA-FBA-20 Topic 13 Question 10 Discussion

Actual exam question for BCS's PC-BA-FBA-20 exam
Question #: 10
Topic #: 13
[All PC-BA-FBA-20 Questions]

A business analyst is reviewing the stakeholder management strategy for a high profile Human Resources (HR) project Following an organisational restructure, Harvey's role has changed from Director of Operations to Director of HR and he has inherited sponsorship of the project Harvey was previously involved in the project, but had little interest because his focus was on the Operational Projects that he sponsored.

Which of the following sets of stakeholder management strategies represent appropriate approaches for Harvey; firstly, for when the project started and secondly now that his role has changed?

Show Suggested Answer Hide Answer
Suggested Answer: C

To determine the appropriate stakeholder management strategies for Harvey, we need to analyze his role and level of interest at two points in time:

When the project started: Harvey was the Director of Operations and had little interest in the HR project because his focus was on operational projects.

Now that his role has changed: As the Director of HR, Harvey has inherited sponsorship of the HR project, making him a key stakeholder with high interest and influence.

Stakeholder Management Strategies:

Watch: This strategy is used for stakeholders with low interest and low influence. It involves monitoring their behavior without actively engaging them.

Constant active management: This strategy is used for stakeholders with high interest and high influence. It involves frequent communication and collaboration to ensure their needs and expectations are met.

Evaluation of Each Option:

A . Keep informed; Constant active management: 'Keep informed' is appropriate for stakeholders with moderate interest but does not align with Harvey's initial lack of interest. Conclusion: This is not correct .

B . Ignore, Constant active management: Ignoring a stakeholder is inappropriate, especially for someone in a senior leadership role like Harvey. Conclusion: This is not correct .

C . Watch, Constant active management:

Initially, Harvey had low interest and low influence on the HR project, making 'watch' an appropriate strategy.

After becoming the Director of HR and inheriting sponsorship, Harvey now requires 'constant active management' due to his high interest and influence. Conclusion: This is the correct answer .

D . Constant active management, keep informed: This reverses the order of strategies and does not align with Harvey's initial lack of interest. Conclusion: This is not correct .


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77