Independence Day Deal! Unlock 25% OFF Today – Limited-Time Offer - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

BCS Exam ISEB-PM1 Topic 8 Question 73 Discussion

Actual exam question for BCS's ISEB-PM1 exam
Question #: 73
Topic #: 8
[All ISEB-PM1 Questions]

A project manager has increased project costs by US $100,000, but completed the project four weeks earlier than planned. What activity is BEST described here?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Tawna
29 days ago
This is easy, it's B) Schedule compression. Though I'm more impressed by the project manager's ability to make the budget disappear than their time-saving skills.
upvoted 0 times
...
Carin
1 months ago
B) Schedule compression, no doubt. The project manager must be a magician to pull off a $100k cost increase and still finish early. I wonder if they have a rabbit in their hat.
upvoted 0 times
A) Resource leveling
upvoted 0 times
...
Martina
11 days ago
C) Critical chain
upvoted 0 times
...
Long
17 days ago
B) Schedule compression
upvoted 0 times
...
...
Melvin
1 months ago
D) Adjusting leads and lags. Wait, what? That doesn't even make sense in this context. I think I need to review my project management notes again.
upvoted 0 times
Stephaine
10 days ago
C) Critical chain. The project manager must have focused on critical tasks to finish early, even with the increased costs.
upvoted 0 times
...
Catarina
11 days ago
B) Schedule compression. It seems like the project manager compressed the schedule to finish early, even if it meant increasing costs.
upvoted 0 times
...
Selma
18 days ago
A) Resource leveling. Maybe the project manager needed to allocate resources more efficiently to finish early.
upvoted 0 times
...
...
Beatriz
2 months ago
I'm not sure if this is a trick question, but I'm going with B) Schedule compression. Seems like the project manager used some extra resources to get the job done quicker.
upvoted 0 times
Felicia
1 months ago
I agree, B) Schedule compression seems like the most logical choice here. The project manager definitely prioritized time over cost.
upvoted 0 times
...
Karan
1 months ago
I would have chosen C) Critical chain, but now that you mention it, B) Schedule compression does seem like the best fit.
upvoted 0 times
...
Clorinda
1 months ago
True, it could be a combination of both B) Schedule compression and C) Critical chain. Efficiency is key.
upvoted 0 times
...
Alise
1 months ago
I think you're right, B) Schedule compression makes sense. It's all about finishing early.
upvoted 0 times
...
Dana
1 months ago
I see your point, but I still think B) Schedule compression fits better. It's about adjusting the timeline.
upvoted 0 times
...
Daniela
2 months ago
But what about C) Critical chain? Maybe the project manager focused on critical tasks to speed things up.
upvoted 0 times
...
Kenneth
2 months ago
I think you're right, B) Schedule compression makes sense. It's all about finishing early.
upvoted 0 times
...
...
Krystal
2 months ago
Ah, the classic 'spend more to save time' conundrum. I'm going with B) Schedule compression - the project manager clearly prioritized completing the project early over keeping costs down.
upvoted 0 times
Sheridan
1 months ago
I think it was a smart move to prioritize finishing early.
upvoted 0 times
...
Mozell
2 months ago
I agree, schedule compression seems like the best option here.
upvoted 0 times
...
...
Nan
2 months ago
I'm not sure, but I think C) Critical chain could also be a possibility. It focuses on managing project constraints.
upvoted 0 times
...
Kenneth
2 months ago
I agree with Kiley. The project manager traded cost for time, so it makes sense.
upvoted 0 times
...
Kiley
3 months ago
I think the answer is B) Schedule compression.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77