In the scope of work (SOW), an interface is described as being installed in the lectern. While the work is underway onsite, the client asks for the interface to be moved to a table next to the lectern. What is the proper response from the technician?
If a client requests a change to the scope of work, such as relocating equipment, the technician should advise the project manager. This ensures that the request is documented and assessed for impact on the project scope, budget, and timeline, maintaining proper project management protocols.
CTS Technology Specialist Reference According to CTS standards, scope changes should be communicated to project management to ensure appropriate adjustments and approvals are made.