The UX team uses a custom issue type named Design in your team-managed project.
You want them to start entering the number of days spent and remaining on each of their issues.
What field must you add to the Design issue type?
The Time tracking field is required to allow users to enter the number of days (or time) spent and the remaining estimate on issues. Adding this field to the Design issue type enables tracking of effort in terms of logged and remaining time.