ASQ Exam CSSBB Topic 9 Question 82 Discussion

Actual exam question for ASQ's CSSBB exam
Question #: 82
Topic #: 9
[All CSSBB Questions]

A project activity not on the critical path has required 20% longer than the time originally allocated. The project team should:

Show Suggested Answer Hide Answer
Suggested Answer: F

Contribute your Thoughts:

Iluminada
2 months ago
Wait, so we're supposed to just tell everyone the project is delayed without actually knowing the extent of the delay? That's a recipe for disaster!
upvoted 0 times
Carman
15 days ago
C) study the effect this will have on other activities because the project may still be on schedule
upvoted 0 times
...
Nieves
16 days ago
B) inform all concerned that the entire project will be delayed but by less than 20%
upvoted 0 times
...
Jerry
17 days ago
A) inform all concerned that the entire project will be delayed by 20%
upvoted 0 times
...
...
Keneth
2 months ago
Option B sounds like the safe bet. It's better to err on the side of caution when it comes to project delays.
upvoted 0 times
Gail
29 days ago
Then we would have to reassess and communicate the new timeline to everyone involved.
upvoted 0 times
...
Tyra
1 months ago
But what if the delay ends up being more than 20% in the end?
upvoted 0 times
...
Lashawn
1 months ago
I agree, it's always better to underpromise and overdeliver.
upvoted 0 times
...
...
Brianne
2 months ago
I think option C is the way to go. Studying the effect on other activities is crucial to understanding the overall impact on the project schedule.
upvoted 0 times
Tomoko
12 days ago
We should definitely take a closer look at the impact on other activities before making any announcements.
upvoted 0 times
...
Kris
24 days ago
Let's analyze the situation before jumping to conclusions. Option C seems like the most logical approach.
upvoted 0 times
...
Marylyn
1 months ago
I agree, we can't just assume the whole project will be delayed by 20%. It might still be on track.
upvoted 0 times
...
Fatima
2 months ago
Option C is definitely the best choice. We need to see how this delay will affect everything else.
upvoted 0 times
...
...
Carolynn
2 months ago
I agree with Alana, we need to assess the impact on other activities before jumping to conclusions.
upvoted 0 times
...
Alana
2 months ago
I disagree, we should study the effect this will have on other activities first before informing everyone.
upvoted 0 times
...
Leonard
2 months ago
I think we should inform everyone that the entire project will be delayed by 20%.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77