ASQ Exam CMQ-OE Topic 2 Question 27 Discussion

Actual exam question for ASQ's CMQ-OE exam
Question #: 27
Topic #: 2
[All CMQ-OE Questions]

The manager for a quality improvement project at an organization receives the project charter during the initiation phase of a project.

'Which of the following information should the expect to find in this document?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Providencia
2 months ago
D sounds like it's going a bit overboard. The project charter is meant to be a high-level document, not a complete risk management plan. A is the way to go here.
upvoted 0 times
Trinidad
2 hours ago
B) The work breakdown description (WBS) for the project
upvoted 0 times
...
Ernest
1 days ago
I agree, the project charter should outline the basic project details.
upvoted 0 times
...
Jesusa
6 days ago
C) The communications plan for this project
upvoted 0 times
...
Carolynn
9 days ago
A) The initial project requirements, constraints, and assumptions
upvoted 0 times
...
Franklyn
15 days ago
B) The work breakdown description (WBS) for the project
upvoted 0 times
...
Elfrieda
1 months ago
C) The communications plan for this project
upvoted 0 times
...
Eileen
1 months ago
A) The initial project requirements, constraints, and assumptions
upvoted 0 times
...
Vi
2 months ago
B) The work breakdown description (WBS) for the project
upvoted 0 times
...
Ciara
2 months ago
A) The initial project requirements, constraints, and assumptions
upvoted 0 times
...
...
Theresia
2 months ago
Haha, I bet the person who wrote option C is the same one who keeps asking for more meetings and PowerPoint slides. The project charter is way too early for a full communications plan.
upvoted 0 times
...
Alva
2 months ago
I was thinking B or D, but after re-reading the question, A definitely makes the most sense. The project charter is about defining the project, not the detailed planning.
upvoted 0 times
...
Barabara
2 months ago
I believe the risk assessment and contingency plans should also be included in the project charter to ensure proactive risk management.
upvoted 0 times
...
Krissy
2 months ago
I agree with Alex. It's important to have a clear understanding of what is expected at the beginning of the project.
upvoted 0 times
...
Alex
2 months ago
I think the project requirements, constraints, and assumptions should be in the project charter.
upvoted 0 times
...
Keena
2 months ago
A seems like the right answer here. The project charter should include the key information about the project scope and constraints, which is what option A describes.
upvoted 0 times
Long
21 days ago
Definitely, without a clear project charter, it can be challenging to keep the project on track and meet the desired outcomes.
upvoted 0 times
...
Luther
29 days ago
Yes, that's correct. The project charter sets the foundation for the project by outlining these key details.
upvoted 0 times
...
Venita
1 months ago
I agree, option A includes the initial project requirements, constraints, and assumptions.
upvoted 0 times
...
Trina
1 months ago
It sets the foundation for the project and helps ensure that everyone is on the same page from the beginning.
upvoted 0 times
...
Breana
1 months ago
User 2: I agree, the project charter is where you would find that information.
upvoted 0 times
...
Huey
1 months ago
Yes, having a clear understanding of the project scope and constraints is essential for successful project management.
upvoted 0 times
...
Brendan
1 months ago
User 1: I think A is the correct answer. It should have the initial project requirements, constraints, and assumptions.
upvoted 0 times
...
Georgeanna
2 months ago
I agree, option A is correct. The project requirements, constraints, and assumptions are crucial to have in the project charter.
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77