Independence Day Deal! Unlock 25% OFF Today – Limited-Time Offer - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

ASQ Exam CMQ-OE Topic 10 Question 85 Discussion

Actual exam question for ASQ's CMQ-OE exam
Question #: 85
Topic #: 10
[All CMQ-OE Questions]

The chart below shows planned costs and actual expenditures. Between times 4 and B the chart indicates which type of cost?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Vallie
2 months ago
This is a classic case of 'the numbers don't lie.' I'd have to go with A) Overrun on this one.
upvoted 0 times
Monroe
1 months ago
Yes, it's definitely an overrun situation based on the chart.
upvoted 0 times
...
Steffanie
2 months ago
I agree, the numbers clearly show an overrun.
upvoted 0 times
...
...
Jeffrey
2 months ago
Ha! Looks like someone's in the doghouse with the finance team. C) Benefit? I don't think so, buddy.
upvoted 0 times
...
Raul
2 months ago
I think it's a benefit cost, as it could be due to unexpected positive outcomes.
upvoted 0 times
...
Devon
2 months ago
I'm going with D) Control. The chart is likely showing the project managers' efforts to get the costs back under control.
upvoted 0 times
...
Benedict
2 months ago
But the chart shows actual expenditures exceeding planned costs, which indicates it's out of control.
upvoted 0 times
...
Valentin
2 months ago
I disagree, I believe it's an overrun cost.
upvoted 0 times
...
Kristofer
3 months ago
B) Out of control seems like the most appropriate choice here. The costs are spiraling out of control based on the information provided.
upvoted 0 times
Lucina
2 months ago
C) Benefit
upvoted 0 times
...
Blair
2 months ago
B) Out of control
upvoted 0 times
...
Leontine
2 months ago
A) Overrun
upvoted 0 times
...
...
Benedict
3 months ago
I think the cost is out of control.
upvoted 0 times
...
Armando
3 months ago
I think the answer is A) Overrun. The chart clearly shows the actual expenditures exceeding the planned costs during that time period.
upvoted 0 times
Candra
2 months ago
It seems like there was definitely a cost overrun between times 4 and B based on the chart.
upvoted 0 times
...
Beata
2 months ago
I think you're right, the actual expenditures went over the planned costs at that point.
upvoted 0 times
...
Detra
2 months ago
I agree, it looks like there was an overrun in costs during that time period.
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77