APM Exam APM-PMQ Topic 3 Question 13 Discussion

Actual exam question for APM's APM-PMQ exam
Question #: 13
Topic #: 3
[All APM-PMQ Questions]

You are the project manager on a construction project for a client in the defence sector. The client has strict regulatory requirements and expects a high level of control and governance throughout the project. Which life cycle would be most suitable?

Show Suggested Answer Hide Answer
Suggested Answer: D

The Linear (or Waterfall) lifecycle is the most suitable for projects that require high levels of governance, control, and strict adherence to regulatory requirements.

Applicability: Linear project management focuses on predefined stages (e.g., requirements, design, implementation) that align with regulatory needs.

Advantages: It allows detailed documentation, structured review processes, and adherence to pre-approved plans, ensuring compliance with defence sector standards.

Alternative Options: Iterative and incremental approaches are less appropriate due to the less structured nature of deliverable evolution in these methods.


Contribute your Thoughts:

Hyman
20 hours ago
I agree with Cristy, Incremental allows for flexibility and incremental delivery.
upvoted 0 times
...
Flo
2 days ago
D) Linear seems like the best choice here. The client's strict regulatory requirements and high control expectations definitely call for a more structured and sequential approach.
upvoted 0 times
...
Cristy
7 days ago
I think the most suitable life cycle would be Incremental.
upvoted 0 times
...