Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

APM Exam APM-PMQ Topic 1 Question 11 Discussion

Actual exam question for APM's APM-PMQ exam
Question #: 11
Topic #: 1
[All APM-PMQ Questions]

You are leading a large-scale information technology project to migrate your company's data to the latest hardware. The delivery is being led by third-party suppliers, who were not involved in the design phase. The supplier has completed their capacity planning and has raised a potential risk that the current data may exceed the storage capacity of the new hardware purchased.

What type of risk response would you choose to mitigate this risk?

Show Suggested Answer Hide Answer
Suggested Answer: C

The best approach is to use the contingency budget because:

Defined Risk Response: Contingency budgets are designed to handle identified risks without impacting the project's main budget.

Stakeholder Agreement: It avoids escalating disputes with suppliers by addressing the issue proactively.

Unsuitable Options:

A: Tolerating the risk is impractical when the risk is confirmed.

B: Re-forecasting creates unnecessary delays and increases costs.

D: Transferring risk to the supplier could damage partnerships.


Contribute your Thoughts:

Avery
5 days ago
I agree with Francisca. It's better to be prepared financially for any unexpected storage needs.
upvoted 0 times
...
Rosina
6 days ago
D. Transfer the risk to the supplier seems like the easiest way out, but that doesn't really address the issue at hand. We need to take responsibility and find a solution within our own resources.
upvoted 0 times
...
Francisca
7 days ago
I think we should re-forecast the budget to include the likely additional cost.
upvoted 0 times
...
Ressie
16 days ago
I think the correct answer is C. Using the contingency budget to cover the purchase of additional storage seems like the most prudent approach. We should be prepared for potential hiccups in a project of this scale.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77