Which one of the following would be expected to form the main part of a risk analysis?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Natalie
2 days ago
D all the way! Identifying whether a risk is a threat or an opportunity is the foundation of the entire risk analysis process.
upvoted 0 times
...
Alaine
4 days ago
I'm going with C. Deciding on the risk response and who's responsible for it is key to actually managing the risks.
upvoted 0 times
...
Gerald
8 days ago
I believe deciding on how to respond to the risk and who should implement the response is also important. We need to have a plan in place to mitigate the risk.
upvoted 0 times
...
Jackie
10 days ago
I agree with Stephane. Understanding the potential impact of the risk is crucial for effective risk management.
upvoted 0 times
...
Stephane
13 days ago
I think evaluating the risk in terms of severity and relative importance would be the main part of a risk analysis.
upvoted 0 times
...
Blythe
13 days ago
Hmm, I think B would be the main part of a risk analysis. Evaluating the severity and importance of the risks is crucial to prioritize them.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77